November 12, 2026
When was the last time a train came up Welton Street? Not since early June. RTD suspended the L Line for its downtown rail reconstruction and said the suspension continues until that project is finished in 2027. The bigger change came on October 27. That night RTD staff presented the board with a plan to repair the line, not rebuild it. CEO Debra Johnson noted the presentation was for discussion, since the board had already approved the project's funding under her guidance.
That plan changes what the tracks are. A full rebuild would have tied Welton to its current layout for decades. A repair would buy time for the city to decide on a different street.
As The Denver Post reported, RTD staff brought a "modified" plan to the Board of Directors. It covers Americans with Disabilities Act and safety upgrades at light rail stations and replaces sections of rail and pavement along the line. Aprajit Desai, RTD's director of infrastructure delivery, told the board the work should keep the line running for another 15 years, with staff checking its condition regularly.
Compare that with the option the city's study set aside. W0, the planned rail replacement in the existing configuration, was not recommended to move forward. The city's public meeting materials said it offered limited public-realm benefits and would lose the chance to substantially change the street for up to 30 years. RTD's 15-year fix fits inside that 30-year window without filling it.
Norman Harris, executive director of the Five Points Business Improvement District, made the case for the repair during public comment at the same meeting:
"Let's bridge to the future design without subjecting Five Points to unnecessary disruption and duplicative construction."
The Post also quoted his summary of the community's position: "What has been established is that the desired future for Welton does not preserve the rail exactly where it is today." Next, RTD negotiates cost and schedule with contractors, including whether the work can be done before the end of 2027.
The city's Welton Next Steps study kicked off in March 2026. It is now in its second alternatives screen, scheduled for fall and winter 2026, with a conceptual design and final plan due in spring 2027. After the first screen, these Welton Street configurations are still in play:
| Configuration | What it means for the street |
|---|---|
| W1, W2, W3 | Side-running layouts with a dedicated transit guideway |
| W7 | Transit sharing lanes with general traffic |
| W8 | Transit moved to a parallel corridor |
| W0, not advanced | Rail rebuilt where it sits today |
The vehicle is also still open. The evaluation covers bus, light rail and streetcar, and the project FAQ says replica trolley vehicles may be explored. The city says it will evaluate converting Welton to two-way traffic. Center-running options, transit-only layouts and autonomous shuttles were all marked not to advance. At the August public meeting, the project team said that setting aside the in-place rebuild did not take rail off the table and that no decision had been made.
Neighbors have been asking for something like this for years. As The Colorado Sun recounted, the 2011 Northeast Downtown Neighborhoods Plan recommended swapping the light rail on Welton for a streetcar to make room for wider sidewalks. In 2012 the Five Points BID asked for a streetcar and a two-way street. The 2004 FasTracks promise to connect Five Points to the A Line stalled in 2014, when an RTD study found the extension "operationally infeasible."
The complaints about the current layout are specific. According to The Colorado Sun, a Five Points BID report said one-way traffic leads to speeding and has made outdoor seating at restaurants nearly impossible. The Post reported that community members described pedestrians feeling squeezed against the train, and service problems from a single track carrying trains in both directions.
The city's first community questionnaire got 486 responses. In the August meeting materials, 73% put better transit as a priority and 89% put a light rail connection to 38th and Blake as a priority. Later meeting notes said the 89% measured support for that connection as a goal, not a vote for a particular alternative. So the people asking for a different street are, by and large, asking for better transit, not less of it.
Phoebe Gryzlo, the city's project manager, described the risk of this in-between period in the Sun's account of the August meeting: "We don't want to see Welton feeling like an empty, quiet corridor."
Route 43 is RTD's stated replacement for the L, running between Central Park Station and the Auraria campus. Its peak frequency has been raised to every 7.5 minutes. It runs on Martin Luther King Boulevard, not on Welton, with a stop at 31st and Downing. That frequency may not last. A proposed change for January 3, 2027 would put Route 43's weekday peak back at every 15 minutes. It is a proposal, not a final change.
Once the repairs are done, RTD plans for restored L service to run from 30th and Downing to at least I-25 and Broadway. Any extension past that is still under consideration.
With no trains, people get to Welton for the places on it. These are the ones that give a December visit a reason, listed in the order you would reach them walking northeast up the street:
A block off the corridor, Rosenberg's Bagels at 725 E. 26th Avenue is open daily from 7 a.m. to 3 p.m.
The biggest night of the month is Five Points First Friday on December 4 at 5 p.m. The BID bills it as a gathering along the whole corridor, with music, local businesses, art, vendors and food. That same night, Cervantes has shows in both rooms. The BID's next public board meeting is December 9 at 10 a.m., with Zoom registration on its site.
The longer timeline stretches further than the 2027 rail work, and each piece depends on the one before it:
RTD staff's 15-year repair plan is meant to keep trains running through that whole sequence and leave the final layout of the street to the city's plan in spring 2027.
If you own a home near Welton and want to know how these plans line up with your block, Ryan Haarer follows the Five Points corridor closely and can walk you through what changes when. Book a consultation, and we'll go over the timeline together.
Stay up to date on the latest real estate trends.
From major residential projects and infrastructure upgrades to new dining and retail, a comprehensive look at what’s changing across the Denver metro this fall
He pays great attention to detail, ensuring his clients make sound, smart real estate choices and investments. Contact him today to discuss all your real estate needs!